Exhibit A – Scope of Work Contract Number:

Contract Period:

Agency Name:

UC Davis PCIT Training Center

Project Name:

Parent-Child Interaction Therapy (PCIT)

Project Length:

Year 1 (09/15/12 – 06/30/13)

Revision Date: (Office Use Only) Report Period:

5 years (09/15/12 – 09/14/17)

Submission Date:

Project Goals: Over a 5-year period, build a network of skilled PCIT trainers and providers in LA County to increase the availability of PCIT for children and families. To achieve this overarching goal and sustain these gains over time, we perceive two phases of training. •



Phase I: builds PCIT training capacity by providing Advanced Training to approximately 98 current PCIT providers in LA County; o Assessment of PCIT services in LA County (Task 1), o Coordination with LACDMH and First 5 LA (Task 2), o Development of an advanced PCIT training program including a method for verifying current PCIT providers’ competencies (Task 3), o Implementation of the curriculum, focused on, but not limited to strengthening agency trainer of trainers’ ToTs training skills (Task 4). The curriculum will have four training platforms:  'PCIT for Traumatized Children' Web Course Advanced PCIT Training Workshop PCIT Training Consultation and Supervision  Post-Assessment Planning Meeting Phase II: builds capacity in PCIT treatment provision by training mental health providers in 20 agencies with no current PCIT program. o Curriculum development (Task 5) o Implementation (Task 6). Certification training will be an 8 month-long training program in three parts:  Program Development:  Fundamental & Skills Building/Evaluation of Skill Acquisition  PCIT Consultation and Supervision

We view these two phases as linked over the five-year training period. • •





Year 1: o o Year 2: o o

Phase I- Current PCIT trainers and providers participate; Curriculum provides trainers with Advanced Skills in training and PCIT treatment provision. Phase II- Therapists from agencies with no current PCIT program learn to provide PCIT. Trainers are identified UCD Advanced PCIT Trainers. Phase I- All current PCIT trainers and providers participate (including Year 1, Phase 2 trainees) Phase II- Therapists from agencies with no current PCIT program learn to provide PCIT. Trainers include several LA County PCIT trainers whose training skills have been certified in Year 1, with UCD Consulting PCIT Trainers supervising them to insure training effectiveness.

Year 3: o Phase I- All current PCIT trainers and providers participate (including Year 2, Phase 2 trainees) o Phase II- Therapists from agencies with no current PCIT program learn to provide PCIT. Trainers include several LA County PCIT trainers whose training skills have been certified in Year 2, with UCD Consulting PCIT Trainers supervising them to insure training effectiveness. Year 4:

-1-

Exhibit A – Scope of Work o o •

Phase I- All current PCIT trainers and providers participate (including Year 3, Phase 2 trainees) Phase II - Therapists from agencies with no current PCIT program learn to provide PCIT. Trainers include several LA County PCIT trainers whose training skills have been certified in Year 3, with UCD Consulting PCIT Trainers supervising them to insure training effectiveness.

Year 5: o Phase I- All current PCIT trainers and providers participate (including Year 4, Phase 2 trainees) o Phase II - Therapists from agencies with no current PCIT program learn to provide PCIT. Trainers include several LA County PCIT trainers whose training skills have been certified in Year 4, with UCD Consulting PCIT Trainers supervising them to insure training effectiveness.

Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. 1. Review background data on the availability of PCIT, and services for 0 to 5 year old children in LA County a. Collaborate with LACDMH to identify all current LACDMH contracted PCIT providers in LA County b. Review, and analyze information on the prevalence and accessibility of PCIT in Los Angeles County. c. Collaborate with LACDMH to obtain information about services and agencies providing services to children aged 0 – 5 in LA County to identify agencies to potentially participate in Phase II training. d. Review and analyze information on the availability of services for children aged 0 – 5 in LA County e. Determine implications of findings for training model 2. Survey LACDMH contracted Agencies providing PCIT services. Find out number of therapists providing PCIT, experience providing PCIT, experience training others to provide PCIT, number of children receiving PCIT, size of agency, support of PCIT program 1. Identify LACDMH and First 5 LA collaborators and develop communications

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

Staff: Urquiza (Director), 10 hrs Timmer (Asst. Director), 20 hrs Forte (Coordinator), 40 hrs Boys (Information Management), 40 hrs Vargas (Administration), 10 hrs

09/15/12 – 10/17/12

1a) Develop list of current LA County PCIT providers by agency and SPA. Due 09/23/12 1b) Disseminate survey of current LA County contracted PCIT providers via Survey Monkey of. Due 09/30/12 1c) Report of analysis of information from review of current PCIT providers. Due 9/30/12 1d) List of services and agencies providing services to children 0 – 5 years in LA County by SPA (Potential Phase II participants). Due 10/06/12 1e) Report of analysis of information from survey of current providers of services for children aged 0-5 years. Due 10/13/12 1f) Brief report on implications of findings of reviews and surveys for Tasks 3 & 5. Due by 10/17/12

Staff: Urquiza, 30 hrs

10/01/12 – 10/30/12

2a) Organizational chart of project collaborators at

1) By October 30, 2012, UCD PCIT Training Center will have reviewed the background data on the availability of PCIT Therapy in LA County and the availability of services for children ages 0-5.

2) By November 30, 2012, Coordinate with First 5 LA and

-2-

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. protocol. 2. Work with LACDMH to develop plan for communicating with and supporting selected Phase I and Phase II PCIT Training sites. 3. Work with LACDMH to develop plan for coordinating and monitoring site renovation and installation of video and telemedicine equipment in selected Phase II agencies, insuring that physical space meets basic needs for PCIT treatment provision. 5. Work with LACDMH to develop plan for coordinating workshops needed for Phase I training. 6. Work with LACDMH to develop plan for coordinate training of agency staff in use and maintenance of video and telemedicine equipment.

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

LACDMH by establishing a memorandum of understanding to ensure coordinated implementation of project strategies.

Timmer, 40 hrs Forte, 40 hrs Boys, 20 hrs Vargas, 10 hrs

-3-

LACDMH, First 5 LA, and UCD PCIT Training Center with contact information and job responsibilities, Due 10/22/12. 2b) Document detailing collaborative strategy and communications protocol with LACDMH, First 5 LA, and training partners. Due 10/24/12. 2c) Set up project management software and network LACDMH, First 5 LA, and PCIT Training partners. Due 10/30/12. 2d) Set up Master Calendar and milestones in Project Management software, including a list of workshops and training events, with technical needs, and estimated numbers. Due 10/30/12. 2e) Detail of collaborative strategies to support participating agencies. Due by 10/6/12 2f) Detail of collaborative strategies for conducting workshops and training events. Due by 10/13/12. 2g) Collaborate to secure locations for workshops and training events as needed. Due 10/7/12. 2h) Plan for coordinating and monitoring agency renovation and installation of equipment. Due by 10/7/12

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks.

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

2i) Plan for coordinating training agency staff in use and maintenance of video and telemedicine equipment. Due by 10/13/12

3) By November 15, 2012, UCD PCIT Training Center will have developed a plan and curriculum to provide Advanced PCIT training to approximately 98 therapists currently providing PCIT services in LACDMH contracted agencies (Phase I Training).

4) By January 30, 2013, UCD

1. Work with LACDMH to develop a plan for recruiting trainees for Phase I Training. 2. Identify all agencies and their executive and clinical directors who could potentially send staff to participate in Phase I Training. 3. Implement recruitment plan by communicating with executive and clinical directors of agencies contracted to provide PCIT services in LA County (potential Phase I Training participants). 4. Develop the Phase 1 Advanced Training curriculum. Define number of training sessions and participation criteria; determine number of required training hours, strategy, platform, and format for delivering training. Include rationale for determining when inperson visits are most appropriate and when it is best to use telehealth equipment. 5. Submit draft Phase I Training Plan to First 5 LA and LACDMH 6. Make adjustments per feedback from First 5 LA and LACDMH and finalize Training Plan. 7. Develop timeline for training. 8. Work with LACDMH and First 5 LA to develop a plan for networking trainers, maintaining ongoing contact, and providing ongoing support to Phase I (ToT) trainees.

Staff: Urquiza, 40 hrs Timmer, 40 hrs Forte, 40 hrs Boys, 30 hrs Vargas, 10 hrs

1. Execute Phase 1 Training according to the approved Final draft of the Advanced

Staff: Urquiza, 30 hrs

09/15/12 – 11/17/12

3a) Draft of Advanced Training design and curriculum. Due 9/22/12 3b) Recruitment plan to enlist Phase I trainees. Due by 10/15/12 3c) Final draft of Advanced Training design and curriculum. Due 10/15/12 3d) Timeline for Advanced Training. Due 10/15/12 3e) Execute recruitment plan by holding Kickoff presentation for Phase 1 agencies, and telephoning executive & clinical directors to describe Phase I training details and timeline. Due by 10/22/12 3f) Final list of Phase I training agencies and participants. Due by 10/30/12. 3g) Plan for networking LA County PCIT trainers, maintaining ongoing contact, and providing ongoing support to Phase I (ToT) trainees. Due 11/17/12

11/22/12 –3/7/13

4a) Conduct initial Advanced Training Phase 1 workshop. Due

Consultants: Zebell, 16 hrs McGrath, 16 hrs

-4-

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. Training plan. Training will include a combination of workshops and in-person site visits with live coaching and feedback, focusing on advanced PCIT skills training and advancing skills of trainers. 2. Conduct evaluation of advanced training by collect baseline, process/ competencies, and post training data on Phase 1 participants for use in evaluation.

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

PCIT Training Center will execute Phase 1 Training, providing Advanced PCIT training to approximately 98 therapists currently providing PCIT services in consenting LACDMH contracted agencies (Phase I Training)

5) By October 24, 2012, UCD PCIT Training Center will develop the Phase II PCIT Training Plan to be used in training 20 LA County contracted agencies to effectively provide PCIT services.

1. Work with LACDMH to develop a plan to recruit an eligible pool of agencies for inclusion in Phase II PCIT training. 2. Work with LACDMH to develop criteria for selecting Phase II agencies. 3. Implement recruitment strategy for Phase II PCIT Training. 4. Select Phase II Agencies 5. Work with LACDMH to coordinate an introductory workshop to inform executive and clinical directors of selected Phase II agencies about program requirements,

Timmer, 164 hrs Forte, 30 hrs Boys, 25 hrs Vargas, 4 hrs

11/22/12. 4b) Schedule for agency site visits. Due 11/29/12 4c) Execute appx 4 -6 site visits. Due 12/14/12 4d) Execute appx 4 -6 site visits. Due 12/21/12 4e) Execute appx 4 -6 site visits. Due 1/8/13 4f) Execute appx 4 -6 site visits. Due1/15/13 4g) Collection of data for evaluation Phase I Training. Due by 1/22/13 4h) Summary report of visits: observations, competencies, future work. Due 2/8/13. 4i) Conduct follow-up Advanced Training Workshop. Due by 2/22/13. 4j) Preliminary report & evaluation of Phase I Advanced Training. Due 3/7/13

Consultants: McGrath, 138 hrs Zebell, 138 hrs

Staff: Urquiza, 20 hrs Timmer, 40 hrs Forte, 20 hrs Boys, 15 hrs Vargas, 6 hrs Consultants: McGrath, 12 hrs Zebell, 12 hrs

-5-

10/06/12 – 11/1/12

5a) Recruitment plan for Phase II trainees, including strategy for underserved and ‘hard to reach’ populations. Due by 10/15/12. 5b) Criteria for Phase II agency selection. Due by 10/06/12 5c) Draft of Phase II Training design and curriculum. Due 10/10/12 5d) Plan for introductory workshop. Due 10/17/12 5e) Final draft of Phase II

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. considerations for selecting trainees, logistical issues connected with implementing PCIT, program effectiveness and benefits for LA County agencies serving young children, general training timelines, billing and reimbursement rates for PCIT services, and training reimbursement. 6. Develop the Phase II Training curriculum. Define number of training sessions and participation criteria; determine number of required training hours, strategy, platform, and format for delivering training. a. Submit draft Phase II Training Plan to First 5 LA and LACDMH b. Make adjustments per feedback from First 5 LA and LACDMH and finalize Phase II Training Plan. 7. Develop timeline for training. 8. With LACDMH and First 5 LA, develop plan for networking LA County PCIT providers and providing ongoing support. 6) By September 1, 2013, CAARE 1. Execute Phase II recruitment plan by will execute Phase II PCIT posting a competitive RFP, combined with Training Plan with a group of 20 other strategies as determined by selected LA County contracted stakeholders. 2. Select 20 agencies to participate in Phase II agencies training. 3. Execute Introductory Workshop for executive and clinical directors of selected Phase II agencies as described in Task 5. 4. Track progress of PCIT equipment installation, coordinating and troubleshooting with LACDMH, as specified in Task 2 5. Prepare trainees for training by instructing them on the use of their video and Include who, what, when, where, how and how much for each objective.

Staff Assignment

Timeline

Deliverables

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

Training design and curriculum per feedback from LACDMH and First 5 LA. Due 11/1/12 5f) Timeline and schedule for training. Due 10/24/12

Staff: Urquiza, 256 hrs Timmer, 575 hrs Forte, 685 hrs Boys, 245 hrs Vargas, 298 hrs Ho, 828 hrs (PCIT Trainer) Torres, 828 hrs (PCIT Trainer) Blacker, 138 hrs (PCIT Trainer) Training Partners: Campbell, 266 hrs Shinn, 266 hrs

-6-

10/24/12 – 07/15/13

6a) Execute Phase II recruitment plan. Due 10/24/12. 6b) List of selected Phase II agencies. Due 11/26/12 6c) Assessment of agency room & equipment installation needs Due by 12/14/12 6d) Hold informational workshop for selected Phase II trainee agencies. Due by 12/21/12. 6e) Obtain and deliver quotes for site renovation & equipment installation progress. Due 12/21/12. 6f) Interim report on agency

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. telemedicine equipment. 6. Execute Phase II Training according to the approved Final draft of the Training curriculum. 7. Collect baseline, process/ competencies, and post training data on Phase II participants for use in evaluation.

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

Pratt, 138 hrs Girard, 266 hrs Consultants: McGrath, 19 hrs Zebell, 19 hrs

-7-

room & equipment installation progress; Due by 2/8/13 6g) Execute plan for training 20 selected Phase II agencies in use and maintenance of video and telemedicine equipment. Due by 2/11/13. 6h) Execute Evaluation/ Skill Building at Phase II agency sites and send interim report. Due 2/28/13 6i) Execute training sessions at Phase II agencies and send interim report on training progress. Due 3/31/13 6j) Execute training sessions at Phase II agencies and send interim report on training progress. Due 4/30/13 6k) Execute training sessions at Phase II agencies and send interim report on training progress. Due 5/28/13 6l) Execute training sessions at Phase II agencies and send interim report on training progress. Due 6/30/13 6m) Collect baseline, progress, and outcomes for clients of trainees. Collect session-bysession training progress notes for each agency, noting trainee progress through PCIT training. Due 7/15/13

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. 1. Collect data to include in quarterly report of implementation activities 2. Prepare quarterly reports

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

7) UCD PCIT Training Center will provide monthly and quarterly implementation reports

8) UCD PCIT Training Center will prepare an annual evaluation report of all (Phase I and Phase II) training activities conducted during the funding period

1. Work with LACDMH to develop plan for coordinating Training Evaluation Design that will meet the evaluation requirements of LACDMH and First 5 LA. 2. Collect and organize data to include in annual evaluation report 3. Prepare annual evaluation report

Staff Urquiza, 32 hrs Timmer, 32 hrs Forte, 14 hrs Boys, 14 hrs Vargas, 11 hrs

09/15/12 to 07/15/13

7a) Memo summarizing activities, deliverables delivered and pending, and action item due dates will be delivered on the first Friday of every month. st 7b) 1 quarter report of 09/15/12 – 12/30/12 implementation activities due by 1/15/13. nd 7c) 2 quarter report of 01/01/13 – 3/30/13 implementation activities due by 04/15/13 rd 7d) 3 quarter report of 04/01/13 – 06/30/13 implementation activities due by 7/15/13

Staff Urquiza, 46 hrs Timmer, 64 hrs Forte, 40 hrs Boys, 40 hrs Vargas, 10 hrs

09/15/12 to 07/15/13

8a) Draft data collection plan due by 10/30/12. 8b) Final data collection plan due 11/15/12. 8c) Collect and organize all outstanding evaluation data. Due by 06/30/13. 8d) Deliver annual evaluation report of activities between 09/15/12 and 06/30/13. Due by 7/15/13 8e) Deliver executive summary of activities between 09/15/12 and 06/30/13. Due by 7/15/13. 8f) Deliver two (2) evaluation or program briefs to First5LA.

-8-

Exhibit A – Scope of Work Objectives

Activities and Subtasks

Staff Assignment

Timeline

Deliverables

Include who, what, when, where, how and how much for each objective.

Indicate the activities and subtasks leading to the fulfillment of the objective. Include benchmarks or milestones in chronological order. Include the appropriate quantity or frequency of the associated activities or subtasks. 1. Develop a Scope of Work for Year 2 of the PCIT Training Project. 2. Develop a Budget for Year 2 of the PCIT Training Project. 3. Collect all supporting documentation for Year 2 Renewal Application.

Indicate staff, consultants or subcontractors responsible for the respective activity or subtask.

Indicate start and end period.

Indicate Date Due.

9) UCD PCIT Training Center will collaborate, prepare and submit necessary documentation for renewing our PCIT Training Project contract for Year 2 by April 30, 2013.

Staff Urquiza, 16 hrs Timmer, 16 hrs Forte, 6 hrs Boys, 4 hrs Vargas, 8 hrs

-9-

03/01/13 to 03/30/13

9a) Deliver Year 2 draft Renewal Application for the PCIT Training Project to First 5 LA. Due by 03/15/13. 9b) Deliver Year 2 final Renewal Application for the PCIT Training Project to First 5 LA. Due by 03/30/13.