Risk opportunity

Risk & Opportunity Management Outline • • • • • • Risk & Opportunity Management Process Risk & Opportunity Registry a...

0 downloads 59 Views 10MB Size
Risk & Opportunity Management

Outline • • • • • •

Risk & Opportunity Management Process Risk & Opportunity Registry and Metrics Qualitative and Quantitative Assessment Risk & Opportunity Impact Modeling Contingency Assessment Next Steps

2

Risk Management is a tool to ensure we are mitigating our highest impact risks • •

Risk Management is required for both DOE and NSF projects It is useful at every stage of the project – NSF: Design and Development Phase and DOE: Pre-CD-0 • Informs the development plan to DOE and NSF. Helps ensure the project is “burning down” the highest risks at the appropriate time with the funds available. • Identifies baseline budget needed for mitigations and “residual risk” contingency



Risk Registry is a systematic way for the scientific and technical staff to communicate to management what the risks are and how we can mitigate them. – It is a record that is updated regularly – Judgement, subjective ➔ leveling or risk review needed – Review top 10/watch list: • Risk re-assessment may change the top risks – Risk mitigation activities needs an approved and budgeted plan – Track action items and progress related to the top risks

• •

Opportunities are also included in the registry Note – this is just “one” tool that is helpful at this early stage and does not substitute the need for “alternative analysis - value engineering” (defining & prioritizing requirements and concept tradeoffs). 3

Risk Registry: Identification, Assessment, Mitigation Planning, Status, and Modeling Proposal •

CM-S4 Risk Registry is currently project’s risk tracking repository : – – – –



Specific Discrete Risks are identified. Qualitative Assessment is recorded/tracked for Current and Post-Mitigation (Residual) levels. Mitigation Planning and Status for each identified risk is tracked directly in the Risk Registry. Registry is fully filter/sortable to aid in tracking / reporting Cost and Schedule risk drivers and associated mitigations, for all identified risks.

Quantitative Assessment and Modeling: – –

Potential cost and schedule impact ranges are calculated and tracked in the registry Cost and Schedule impact ranges are applied directly to schedule and cost Monte Carlo models or other statistical methods could be calculated to develop discrete risk contingency estimates. Code macro for google

Risk Identification & Current Assessment Fields are required. 4

Risk Registry: Identification, Assessment, Mitigation Planning, Status, and Modeling (2)

Data for Monte Carlo Probability > 10%

5

Definition of Risk and Risk Analysis • • •

Risk can be defined as an undesirable event during project execution that negatively effects program goals for performance, cost or schedule. Risk management is the ongoing process of comprehensively assessing project risks. Risk Management Plan (TBD) defines the methodology to manage our risks

→Objective qualitative process to assign values to probability of occurrence and impact of occurrence aspects of risk. →Total Impact: (0.33*Cost Impact) + (0.33*Schedule Impact) + (0.33*Performance Impact) →Risk Score: Risk Probability * Total Impact

6

Readout Performance, Schedule and Cost Burndown Plan (Preliminary Assessment)

7

Example: Risk Analysis – Contingency Assessment • Cost estimate contingency assessed at the lowest WBS level

• Contingency Assessment (Bottoms-up + Discrete Risks + Unknowns) = • $22.17M + $8.64M + $4.34M = $35.15M Contingency (TPC) • Opportunities to generate additional contingency: • CAM-033 Sensor Cost: potential for $5-10M cost reduction. • CAM-010 Exchange Rate: potential for $2.5M cost reduction. 8

Risk management near term support needed from technical collaboration Identify major risks

Define current exposure level

Develop mitigations Perform Post-Mitgation exposure level 9

End of Presentation • Link to CMB-S4 Risk and Opportunity folder – https://drive.google.com/drive/u/1/folders/1U5eCZakq-rj6VJ7Et6A4H__Oq2_Shxq2

10

Other available tools - Google form

11

Summary of Risks (CDT Example)

12

Example: CMB-S4 Current Top Technical Risks (Preliminary) Risk Title

Risk Description (if/then)

Current Exposure

Residual Exposure

Integrated FP Performance

IF end-to-end noise floor in science band exceeds (e.g. >20% of in-band background limit) in yielded packages THEN reduces experiment sensitivity and/or increases cost/schedule

23.3

Critical

12.0

Moderate

Wafer sustained yield

IF decrease in fab or performance yield over production period (define criterion) THEN reduces experiment sensitivity and/or increases cost/schedule

23.3

Critical

9.3

Minor

MUX factor

IF achieved MUX factor < (e.g. 128 or 512) THEN increases qty + complexity of cold MUX and increases cost/schedule

20.0

High

9.0

Minor

MUX Noise

IF integrated noise of readout electronics is greater than 50% of predicted photon noise limit THEN it will reduce system mapping spped by >20%

18.3

High

9.0

Minor

Detector Testbed reliability

IF 1-2 fully characterized test beds doesn't exist THEN throughput reduction and/or increase cost/schedule

18.3

High

6.0

Minor

Readout Testbed reliability

IF 1-2 fully characterized test beds don't exist THEN throughput reduction and/or increase cost/schedule

18.3

High

6.0

Minor

FP I&T Testbed reliability

IF 1-2 fully characterized test beds don't exist THEN throughput reduction and/or increase cost/schedule

18.3

High

6.0

Minor

Sensor Performance

IF wafer performance yield < (eg.80-90%); (yield = Sensor parameter variation (e.g., Psat, Rn, L) meet spec for wafer) THEN reduces experiment sensitivity and/or increases cost/schedule

16.7

High

7.0

Minor

MUX integration yield

IF integration yield < 80% THEN reduces experiment sensitivity and/or increases cost/schedule

16.7

High

8.0

Minor

16.0

High

9.0

Minor

16.0

High

10.7

Moderate

15.0

Moderate

7.0

Minor

FP performance: stability

Wafer Fab Yield Cryostat Assembly complexity

IF end-to-end low-frequency noise in science band exceeds (e.g.>20% of inband background) THEN reduces experiment sensitivity and/or increases cost/schedule IF wafer fabrication yield