Chapter4

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan CHAPTER 4: COST ESTIMATE METHODOLOGY LAND USE ...

0 downloads 88 Views 281KB Size
The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

CHAPTER 4: COST ESTIMATE METHODOLOGY LAND USE AND STREETSCAPE IMPROVEMENTS Cost estimates for the recommended streetscape improvements in the US 50 Corridor are conceptual, planning-level estimates that are based on sample private development projects from other communities that contain these types of similar streetscape elements. These costs do not include location-specific land use development opportunities; they are solely streetscape costs along the corridor. It is assumed that public funds would be used to make the streetscape improvements, therefore costs were increased by 15 percent to account for prevailing wage requirements and contractor qualification procedures. A 20 percent contingency was also added to compensate for the planning level of detail. Below is a specific description of the methodology used for estimating costs of streetscape elements for each section of the US 50 corridor. Figure 4-1 includes more detailed information regarding the streetscape costs and can be found at the end of this chapter. A summary of the streetscape costs for each sub-section of the corridor is included in Figure 4-2. Figure 4-2: Sub-Section Summary Project Costs Sub-Section

Streetscape Costs

Access Management Costs

Project Total

Stateline Road to I-275/SR 1 I-275/SR 1 to Argosy Parkway Argosy Parkway to Walnut Street/Stadium Lane Walnut Street/Stadium Lane to Front Street Front Street to SR 48

N/A $700,000 $40,000

$3,500,000 $3,000,000 $1,000,000

$3,500,000 $3,700,000 $1,040,000

$500,000

$500,000

$1,000,000

$50,000

$600,000

$650,000

SR 48 to Tanners Creek Road

$200,000

$2,000,000

$2,200,000

Tanners Creek Road to Wilson Creek Road Wilson Creek Road to SR 148

$700,000

$3,000,000

$3,700,000

$600,000

$4,000,000

$4,600,000

SR 148 to George Street

N/A

$200,000

$200,000

George Street to SR 350

N/A

$500,000

$500,000

SR 350 to SR 62

N/A

$14,000,000*

$14,000,000

* Includes extensive drainage work to install curb

Sidewalks Cost estimates for sidewalk construction were based on a cost of $4 per square foot for installation of a four inch thick sidewalk, including the base. Proposed sidewalk square footage was estimated by measuring length with GIS software, and multiplying the length by an assumed width of eight feet, a typical sidewalk width.

January 2007

Page 4-1

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

The same methodology was applied to estimates for sidewalk widening in the Argosy Parkway to SR 48 section. In this case, however, the width used was six feet, to account for the widening of existing sidewalks from six feet (estimated existing width) to 12 feet. Replacing Pavement with Treelawns Since treelawns are proposed to replace portions of existing parking lots and driveways to be closed, a cost estimate was developed for demolition and disposal of asphalt, clean fill backfill and topsoil dress, and hydro-seeding with grass. This cost was estimated at $4.50 per square foot. Total square footage of proposed replacement of pavement with treelawns was estimated by measuring the length of these areas with GIS software, and multiplying the length by an assumed width of 10 feet. Tree Planting Trees are recommended in center medians, along treelawns, and in some areas, sidewalk grates (see Exhibit 4-1). Costs can vary from $400 to $600 per tree depending on the type of the tree. In this case, the middle of this range, $500, was used. The number of proposed trees was estimated by measuring the lengths of areas in which trees are to be planted with GIS software, and dividing the length by the distance between trees. Throughout most of the corridor, this distance is 35 feet. Between Argosy Parkway and SR 48, this Exhibit 4-1: Tree Planting/ Ornamental distance is 25 feet, recognizing the slower Wall/Fence traffic and pedestrian scale of this area. Ornamental Wall/Fence This feature is only proposed between Argosy Parkway and SR 48 (see Exhibit 4-1). The proposed type of wall/fence combination is a three foot tall decorative metal fence (such as wrought iron) interspersed with sections of masonry wall with a limestone cap. Roughly 25 percent of this wall/fence is masonry, which costs approximately $150 per linear foot. The remaining 75 percent would be ornamental metal fencing, which costs approximately $85 per linear foot. Landscape Beds Landscape beds with flowers and shrubs are proposed at community gateways and key development nodes. The installation cost of a landscape bed is approximately $8 per square foot. Square footages of planting beds at various locations were estimated as follows: January 2007

Page 4-2

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ƒ

Ohio/Indiana state line

ƒ

Regional gateway at intersection of US 50 and I-275: 6,000 square feet

ƒ

Intersections of Lorey Lane and Urban Way with US 50: 1,000 square feet each

ƒ

Local gateway at Lawrenceburg/Aurora boundary: 2,500 square feet

Gateway Signage Gateway signage is proposed at three locations: the I-275 interchange, the Lawrenceburg/Aurora boundary Exhibit 4-2: Gateway Signage and the Ohio/Indiana state line. A decorative ground-mounted sign with a masonry frame and base, roughly 11 feet wide and four feet tall, was estimated to cost between $6,000 and $8,000 (see Exhibit 4-2). Raised Crosswalks This feature was recommended only between Argosy Parkway and SR 48. The estimated cost of a raised, stamped concrete crosswalk is $16 per square foot. Square footage was calculated by assuming a 55 foot length and a 12 foot width for each crosswalk. Street Lamps This feature, proposed only between Argosy Parkway and SR 48, was estimated to cost between $3,500 and $4,000 per street lamp, assuming a double-fixture, decorative design similar to the design illustrated below (see Exhibit 4-3). The cost estimates for this report used the average of this range, which is $3,750. Exhibit 4-3: Street Lamps

January 2007

Page 4-3

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ACCESS MANAGEMENT IMPROVEMENTS The estimated project cost is a construction cost estimate for the recommended improvements. These costs were considered to be at a planning level, thus a 10 to 20 percent contingency was added to each cost along with an overall 20 percent contingency. The following are assumptions for the access management improvements only; the land use improvement cost assumptions were discussed previously in this chapter. Figure 4-3 provides the details of the cost estimate and can be found at the end of the chapter. A summary of the sub-section project costs is included in the Figure 4-2. Curb A Type 6 curb (6 foot curb) would be installed the entire length of the project. Dives and or entrances would be saw cut as needed. At this point in the project development process, it is a good assumption that the entire curb would need replacement. This assumption may change as the project is designed in more detail. Right-in/Right-out Islands Right-in/right-out traffic islands shall be constructed as shown, which would consist of 42.33 square yards of 6 foot wide concrete. Service Roads Two-way and or one-way service roads would be constructed using 6 feet of aggregate base, 4 feet of asphalt concrete base and 3 feet of asphalt concrete. Proposed lane widths would be 12 feet minimum. Excavation A quantity of excavation would be needed for the removal of flexible pavement in the proposed median area and where driveways are noted as removed. Embankment Material for Median Embankment material would be needed for the placement of suitable material in the landscaped median area and behind the proposed curb along the edge of pavement as needed. Drainage Currently, a ditch system is utilized to carry water run-off on many sections of US 50. A drainage system would be needed if curb is installed. This can be a costly improvement. The benefits and costs of constructing a curb the entire length of US 50 would need to be further investigated, particularly in Section 4 from SR 350 to SR 62. This drainage system should include catch basins spaced at every 250 feet, manholes spaced at 500 feet and an average of 30 inch concrete pipe connecting the drainage system and outletting to an approved outfall.

January 2007

Page 4-4

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

Signage Signing, including post installations for such signs as “One Way”, “Stop” and “No Left Turn” should be installed as shown on the plans. Raised Median A 10 foot wide raised concrete median referred to as the landscaped median should be constructed where two-way left turn lanes presently exist. The cost for the concrete median would consist of pavement excavation, a 6 foot concrete curb, embankment material, 3 feet of topsoil, seeding and mulching. This number does not assume landscaping; only the topsoil and base that landscaping would require.

January 2007

Page 4-5

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

Figure 4-1: Streetscape Costs

Unit Corridor Section

Cost per unit Total Units 275-Argosy Parkway Total Cost Total Units Argosy-Walnut Total Cost Total Units Walnut to Front Total Cost Total Units Front to SR 48 Total Cost Total Units SR 48 to Tanners Creek Total Cost Total Units Tanner's Creek to Wilson Creek Total Cost Total Units Wilson Creek to SR 148 Total Cost

State wage and contractor requirements Contingency

New Sidewalk

Widen Sidewalk

Treelawn to replace pavement

Square feet

Square feet

Square feet

Lineal Feet, Tree Portion of Median

Trees

$4 59296 $327,314 6,864 $37,889 0 $0 0 $0 21,848 $120,601 65,960 $364,099 43,016 $237,448

$4 0 $0 0 $0 10,650 $58,788 0 $0 0 $0 0 $0 0 $0

$4.50 12820 $79,612 0 $0 0 $0 0 $0 5,570 $34,590 8,610 $53,468 33,140 $205,799

n/a 4463 n/a 0 n/a 735 n/a 0 n/a 0 n/a 4,531 n/a 2,935 n/a

$500 128 $87,985 0 $0 29 $20,286 0 $0 0 $0 129 $89,325 84 $57,861

Trees in Median

Flower Beds

Signs

Ornamental Fence/Wall

Street lamps

Stamped concrete crosswalks

Trees

Square feet

Sign

Lineal feet

Lamp

Square feet

$500 207 $143,067 0 $0 71 $48,990 0 $0 99 $68,645 253 $174,747 161 $111,208

$8 8000 $88,320 0 $0 0 $0 0 $0 0 $0 2,500 $27,600 0 $0

$6,000 1 $8,280 0 $0 0 $0 0 $0 0 $0 2 $16,560 0 $0

$101.25 0 $0 0 $0 1117 $156,073 0 $0 0 $0 0 $0 0 $0

$3,750 0 $0 0 $0 29 $152,145 0 $0 0 $0 0 $0 0 $0

$16 0

Trees, Treelawn/sidewalk grates Lineal Feet, Treelawn or widened sidewalk n/a 7257 n/a n/a n/a 1775 n/a n/a n/a 3,482 8,864 5,641

TOTAL

$734,578 0 $0 660 $14,573 1,980 $43,718 0 $0 0 $0 0 $0

$37,889 $450,855 $43,718 $223,836 $725,800 $612,317

15% 20%

January 2007

Page 4-6

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

Figure 4-3: Cost Estimates DRAINAGE

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

42.33

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

SECTION 1 Stateline Road to I-275/SR 1 12 4 9 10 17

1 1 1 1 2

Total Length (miles) = 2

Driveway Driveway Driveway Driveway Driveway

21 22 19 300 100

TOTAL

GRAND TOTAL COST PER ITEM

TOTAL COST

I-275/SR 1 to Argosy Parkway 22A 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 45 46 48 49

3 3 3 3 3 3 3 3,4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 5 5

GRAND TOTAL COST PER ITEM

TOTAL COST

Driveway - Walgreens Driveway - Walgreens Driveway Driveway Driveway - Shell & Subway Driveway - Ande Chevrolet Driveway Unsignalized Intersection Driveway - Tire Center Driveway - Discount Store Driveway - Tire Center Driveway - Whiskey Cold Beer Driveway - Wishing Well Motel Driveway - Wishing Well Motel Driveway - Wishing Well Motel Driveway - Quality Inn Driveway - Marathon Gas Station Driveway - Truck Stop Driveway - M&M Automotive Unsignalized Intersection Driveway - Site redevelopment Driveway - Chrysler Driveway - Mixed small retail Unsignalized Intersection Unsignalized Intersection Driveway - Ford Dealership Driveway - Ford Dealership

15

21120

0

400

0

77

0

86

44

25344

0

0

0

0

0

0

0

0

0

21120

0

400

0

77

0

86

44

25344

0

0

0

0

0

0

0

0

0

$13

$55

$160

$80

$7

$5

$3,000

$3,500

$85

$12

$12

$12

$6

$13

$7

$5

$35

$1

$274,560

$0

$64,000

$0

$537

$0

$259,440

$154,840

$2,154,240

$0

$0

$0

$0

$0

$0

$0

$0

$0

$339,097

$2,568,520

$0

ESTIMATE CONSTRUCTION COST CONTINGENCY COST (20%)

$2,907,617 $581,523

Stateline Road to I-275/SR 1 TOTAL COST

$3,489,140

$0

Total Length (miles) = 1.4 44 28 27 64 27 2.25

12

29 Walnut Street

150

400

12.5

24

26 25 32 2.25

12

2.25 2.25 2.25

12 12 12

12 32

66 2.25 Faith Way - Median Break

430

1000

6.25

12 12

6.25 6.25

12 12 12 12

24 2.25 2.25 Unnamed - Median Break McClure Way - Median Break 25 33

14784

2053

2738

684

8213

16684 $13

0 $55

680 $160

100

0 $80

494 $7

0 $5

69 $3,000

35 $3,500

20021 $85

18 $12

31 $12

0 $12

156 $6

14784 $13

2053 $7

2738 $5

684 $35

8213 $1

$216,892

$0

$108,800

$0

$3,457

$0

$206,208

$123,788

$1,701,768

$216

$375

$0

$936

$192,192

$14,373

$13,689

$23,956

$8,213

500

$329,149

$2,031,764

$1,527

$252,423

ESTIMATE CONSTRUCTION COST

$2,614,863

CONTINGENCY COST (20%)

$522,973

I-275/SR 1 to Argosy Parkway TOTAL COST

$3,137,836

GRAND TOTAL SECTION 1 COST

$6,626,976

January 2007

Page 4-7

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

DRAINAGE EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

42.33

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

SECTION 2 Argosy Parkway to Walnut Street/ Stadium Lane 51 54 56

5 5 5

Driveway Driveway Unsignalized Intersection

Total Length (miles) = 0.6 8 42.33 126.99

Third Street

GRAND TOTAL COST PER ITEM

TOTAL COST

2.25

6336 $13

169 $55

0 $160

0 $80

8 $7

0 $5

27 $3,000

15 $3,500

7603 $85

2 $12

0 $12

0 $12

12 $6

0 $13

0 $7

0 $5

0 $35

0 $1

$82,368

$9,313

$0

$0

$54

$0

$82,032

$51,352

$646,272

$27

$0

$0

$72

$0

$0

$0

$0

$0

0 $5

0 $35

0 $1

$0

$0

$0

$91,735

Walnut Street/ Stadium Lane to Front Street 58 59 60 61 B 61 62 63 64 65 66 67 68 69 70 71 72

5 5 5 5 5 5 5 5 5 5 5 5,6 5,6 5,6 6 6

Driveway - A1 Auto Driveway - KFC Driveway - KFC Driveways - Boat Shop and Service Driveway - Alley Driveway - Bill's Service Car Repair Driveway - KFC Driveway - Bill's Service Car Repair Driveway - Fehrman Realty Driveway - Glass Pro Driveway - Fehrman Realty Driveway - Glass Pro Unsignalized Intersection Driveway Driveway - Whisky's Driveway Driveway

$779,656

CONTINGENCY COST (20%)

$174,298

Argosy Parkway to Walnut Street/ Stadium Lane TOTAL COST

$1,045,788

Total Length (miles) = 0.21

TOTAL COST

12 12

2.25

12

33 21 50 28 Water Street 400 42.33

2.25 2.25 2.25

6.25

3.00 3.00

36 12

6 $12

84 $6

0 $13

0 $7

$72

$504

$0

$0

17

Front Street to SR 48

GRAND TOTAL COST PER ITEM

2.25 2.25

300

2618 $13

42 $55

0 $160

$34,029

$2,328

$0

300 $80

224 $7

0 $5

12 $3,000

$24,000

$1,567

$0

$37,411

$61,924

Unsignalized Intersection Driveway Unsignalized Intersection Unsignalized Intersection

$0 $871,490

9 21

TOTAL COST

6 6 6 6

$99

ESTIMATE CONSTRUCTION COST

32 13

GRAND TOTAL COST PER ITEM

74 76 77 79

12

7 $3,500

3141 $85

14 $12

6 $12

$25,323

$266,995

$162

$75

$329,730

$813

$0

ESTIMATE CONSTRUCTION COST

$392,467

CONTINGENCY COST (20%)

$78,493

Walnut Street/ Stadium Lane to Front Street TOTAL COST

$470,960

Total Length (miles) = 0.32 Park Street

42.33

3.00

Shipping Street Unnamed

9 17 11

22

6.25

12 12

3379 $13

42 $55

0 $160

0 $80

37 $7

22 $5

16 $3,000

9 $3,500

4055 $85

0 $12

6 $12

3 $12

24 $6

0 $13

0 $7

0 $5

0 $35

0 $1

$43,930

$2,328

$0

$0

$258

$111

$46,550

$30,654

$344,678

$0

$75

$36

$144

$0

$0

$0

$0

$0

$46,627

$421,883

$255

$0 $468,765

ESTIMATE CONSTRUCTION COST CONTINGENCY COST (20%)

$93,753

Front Street to SR 48 TOTAL COST GRAND TOTAL SECTION 2 COST

$562,518 $2,079,267

January 2007

Page 4-8

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

DRAINAGE EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

42.33

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

0 $5

0 $35

0 $1

$0

$0

$0

SECTION 3 SR 48 to Tanners Creek Road 81 82 83 84 85 86 87 89 90 91 93 100 101 102 103 104 106

6 6 6 6 6 6 6 6 6 6 6 6,7 7 7 7 7 7

Driveway Driveway Driveway - Water Treatment Plant Driveway - Kroger Driveway Driveway Driveway Unsignalized Intersection Driveway Driveway - K&K Mini Mart, Jones Driveway - Real Estate Services Driveway - Car Wash Driveway - Small Retail Driveway - Skyline Driveway - Classic Car Wash Driveway Unsignalized Intersection

Total Length (miles) = 1.03 21 22 6.25 42

12 12

2.25 16 20 14

Doughty Road

6.25 200 200 200 250

40

400

80

12

200 40 70

3.00

12

3 $12

60 $6

0 $13

0 $7

$36

$360

$0

$0

9

22 7 County Road 5

6.25

GRAND TOTAL COST PER ITEM

TOTAL COST

12127 $13

42 $55

230 $160

$157,648

$2,328

$36,800

220 $80

111 $7

0 $5

51 $3,000

$17,600

$780

$0

$151,522

$215,156

26 $3,500

14552 $85

2 $12

19 $12

$91,888

$1,236,934

$27

$225

$1,480,343

12

$648

$0 $1,696,147

ESTIMATE CONSTRUCTION COST

Tanners Creek Road to Wilson Creek Road 109 110 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 138 140 141 142

7 7,8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8

Driveway - Art Deco Residence Driveway - Golden Corral Driveway - Pizza Hut Driveway - Garden Center Driveway - Garden Center Driveway - Papa John Unsignalized Intersection Driveway - Open land Driveway - Speedway Driveway - Speedway Driveway - Abandoned building Driveway - Abandoned building Driveway - Auto Zone Driveway - Frish's Driveway - Frish's Unsignalized Intersection Driveway - Pro Outdoors Driveway - Movie Gallery Driveway - Art's Rental Driveway - US Bank Driveway - US Bank Driveway - Beers Auto Sales Driveway - Small Retail Driveway - Beers Auto Sales Driveway - Beers Auto Sales Driveway - Advance Auto Parts Driveway - Do it Best Hardware Driveway - Indiana Monument Driveway - Modular home Driveway - Long John Silvers

CONTINGENCY COST (20%)

$339,229

SR 48 to Tanners Creek Road TOTAL COST

$2,035,376

Total Length (miles) = 1.11 2.25 2.25 2.25 200 200

30 30

300 100 100 300

50

12 12 12

16 14 14

Shurlite - Median Opening

6.25 21 20 20

12

20 20

40

2.25

12

2.25

12

24 19 36 Florence Drive - Median

1000 250

140 40

300 100 100

40

12.50 29 21 17 20 20 12

24

20 20

900

900

3.00

12 12

3.00

12

11722

1628

2171

543

6512

6 $12

132 $6

11722 $13

1628 $7

2171 $5

543 $35

6512 $1

$72

$792

$152,381

$11,396

$10,853

$18,993

$6,512

2.25 37 16 40

200

GRAND TOTAL COST PER ITEM

TOTAL COST

15772 $13

0 $55

410 $160

$205,031

$0

$65,600

25 20 27

900 $80

427 $7

80 $5

65 $3,000

$72,000

$2,987

$400

$195,259

$346,017

34 $3,500

18926 $85

14 $12

19 $12

$117,401

$1,608,703

$162

$225

$1,921,364

$1,251

$200,135 $2,468,768

ESTIMATE CONSTRUCTION COST

Wilson Creek Road to SR 148 144 145 146 147 148 149 150 151 153 154

9 9 9 9 9 9 9 9 9 9

Unsignalized Intersection Driveway - Insurance Driveway - Insurance Driveway - Dairy Queen Driveway - Glass shop Driveway - Ashcroft / Auto body Driveway - Far East Driveway - Far East Driveway - Riverside Car Sales Driveway - Riverside Car Sales

CONTINGENCY COST (20%)

$493,754

Tanners Creek Road to Wilson Creek Road TOTAL COST

$2,962,521

Total Length (miles) = 1.95 Hillcrest Drive - Median

6.25

12

11 200

70

2.25 2.25

12 12

2.25

12

2.25

12

2.25

12

61 9 15

January 2007

Page 4-9

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

DRAINAGE EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

42.33 155 156 157 158 159 161 162 163 164 165 166 167 168 169A 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184

9 9 9 9 9 9 9 9 9 9 9 9 9 9

Driveway - All American Carwash Driveway - American Rental Driveway - Besslers Restaurant Driveway - Victory crafts Unsignalized Intersection Driveway - Riverside sales Driveway - Poor House Liquior Driveway - Riverside sales Driveway - house Driveway - Red Dog Driveway - Carpet World Driveway - Red Dog Gas Station Driveway - Trade Winds Marine Help U Sell Driveway - residential Driveway - Locksmith Driveway - residential Driveway - Small Retail, Subway Driveway - residential Driveway - BP Driveway - BP Driveway - Family Dollar Driveway - residential Driveway - Family Dollar Driveway - Walgreens Driveway - Walgreens Driveway - Family Dollar Driveway - Swifty Gas

9

Driveway - Swifty Gas

9 9 9 9 9 9 9 9 9 9 9 9 9

GRAND TOTAL COST PER ITEM

TOTAL COST

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

2.25

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

12

86 106 73 Boat Ramp - Median Opening

12.5 16 22 20 5 20

100

20 26

100

60

400

24

20 20

2.25 2.25

12 12

2.25 2.25

12 12

2.25

12

2.25 2.25

12 12

2.25 2.25

12 12

15 79

28

17

30

200

139 15 56 18

2.25

12

2.25

12

21592 $13

0 $55

160 $160

0 $80

855 $7

40 $5

88 $3,000

45 $3,500

25910 $85

38 $12

19 $12

0 $12

240 $6

0 $13

0 $7

0 $5

0 $35

0 $1

$280,696

$0

$25,600

$0

$5,985

$200

$265,104

$158,144

$2,202,384

$459

$225

$0

$1,440

$0

$0

$0

$0

$0

$312,481

$2,625,632

$2,124

$0 $2,940,237

ESTIMATE CONSTRUCTION COST CONTINGENCY COST (20%)

$588,047

Wilson Creek Road to SR 148 TOTAL COST

$3,528,284

January 2007

Page 4-10

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

DRAINAGE EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

42.33 SR 148 to George Street 186 187 188 189 190

9,10 9,10 9,10 9,10 10

Unsignalized Intersection Driveway Driveway Driveway Driveway

TOTAL

GRAND TOTAL COST PER ITEM

TOTAL COST

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

Harrison Street

George Street to SR 350

GRAND TOTAL COST PER ITEM

TOTAL COST

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

13 17 13 13 29 1056

0

0

0

86

0

6

4

1267

0

0

0

0

0

0

0

0

0

1056 $13

0 $55

0 $160

0 $80

86 $7

0 $5

6 $3,000

4 $3,500

1267 $85

0 $12

0 $12

0 $12

0 $6

0 $13

0 $7

0 $5

0 $35

0 $1

$13,728

$0

$0

$0

$599

$0

$18,672

$14,392

$107,712

$0

$0

$0

$0

$0

$0

$0

$0

$0

$140,776

$0

$0 $155,103

ESTIMATE CONSTRUCTION COST

10 10 10 10 10 10

EMBANKMENT (CU YD) Note: 5

Total Length (miles) = 0.1

$14,327

193 194 196 197 198 200

EXCAVATION (CU YD) Note: 4

CONTINGENCY COST (20%)

$31,021

SR 148 to George Street TOTAL COST

$186,123

Total Length (miles) = 0.3

Driveway Driveway Driveway Driveway Driveway Driveway

17 34 8 12 18 21

3168 $13

0 $55

0 $160

0 $80

111 $7

0 $5

15 $3,000

8 $3,500

3802 $85

0 $12

0 $12

0 $12

0 $6

0 $13

0 $7

0 $5

0 $35

0 $1

$41,184

$0

$0

$0

$774

$0

$44,016

$29,176

$323,136

$0

$0

$0

$0

$0

$0

$0

$0

$0

$41,958

$396,328

$0

$0 $438,286

ESTIMATE CONSTRUCTION COST CONTINGENCY COST (20%)

$87,657

George Street to SR 350 TOTAL COST GRAND TOTAL SECTION 3 COST

$525,943 $9,238,248

January 2007

Page 4-11

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

DRAINAGE CATCH BASIN (EACH) Note: 6

TRAFFIC CONTROL NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

42.33

2.25

6.25

3.00

42 42 42 42

2.25 2.25 2.25 2.25 2.25 2.25

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

MANHOLE (EACH) Note: 7

PIPE (FT) Note: 8

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

0 $5

0 $35

0 $1

$0

$0

$0

SECTION 4 SR 350 to SR 62 202 203 205 207 208 209 219 240 270 325 331 335 339 343 347 348 349 350 351 352 390

10 10 11 11,12 12 12 13 13 14 17 17 17 17 17 17 17 17 17,18 18 18 19

GRAND TOTAL COST PER ITEM

TOTAL COST

Unsignalized Intersection Unsignalized Intersection Unsignalized Intersection Unsignalized Intersection Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Driveway Unsignalized Intersection Driveway Driveway

Total Length (miles) = 8.4 Exporting Street Unnamed Indiana Avenue Lower Dillsboro Road

20 20

100 100

20 20

12 12 12 12 12 12

8 140 13 12 20 17 12 27 27 24 16 16 24 24

Sharon Drive

88904 $13

169 $55

140 $160

$1,155,752

$9,313

$22,400

0 $80

281 $7

40 $5

358 $3,000

$0

$1,964

$200

$1,072,848

$1,189,628

180 $3,500

106685 $85

14 $12

0 $12

$629,328

$9,068,208

$162

$0

$10,770,384

0 $12

72 $6

0 $13

0 $7

$0

$432

$0

$0

$594

$0 $11,960,606

ESTIMATE CONSTRUCTION COST CONTINGENCY COST (20%)

$2,392,121

SR 350 to SR 62 (SECTION 4) GRAND TOTAL COST

$14,352,728

January 2007

Page 4-12

The Southeastern Indiana Gateway: US 50 Transportation and Land Use Plan

ROADWAY

Access ID Map Sheet # #

Access Type

Intersecting Street Name

6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

DRAINAGE EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

TRAFFIC CONTROL

PIPE (FT) Note: 8

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

2.25

6.25

3.00

42.33

10 FT WIDE LANDSCAPED MEDIAN GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

PROJECT SUMMARIES 6"CONCRETE TYPE 6 CURB TRAFFIC ISLAND (FT) (SY YD) Note: 1 Note: 2

SERVICE ROAD (TWO-WAY) Note: 3

SERVICE ROAD (ONE-WAY) Note: 3

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

CATCH BASIN (EACH) Note: 6

MANHOLE (EACH) Note: 7

PIPE (FT) Note: 8

NO LEFT TURN SIGN (SQ FT) Note: 9

STOP SIGN (SQ FT) Note: 10

ONE WAY SIGN (SQ FT) Note: 11

GROUND MOUNTED SUPPORT (FT) Note: 12

TYPE 6 CURB (MEDIAN) (FT) Note: 13

EXCAVATION (CU YD) Note: 4

EMBANKMENT (CU YD) Note: 5

TOPSOIL FURNISHED AND PLACED (CU YD) Note: 14

SEEDING AND MULCHING (SQ YD) Note: 15

0 $0

494 $3,457

0 $0

69 $206,208

35 $123,788

20021 $1,701,768

18 $216

31 $375

0 $0

156 $936

14784 $192,192

2053 $14,373

2738 $13,689

684 $23,956

8213 $8,213

37 $258

22 $111

16 $46,550

4055 $344,678

0 $0

6 $75

3 $36

24 $144

0 $0

0 $0

0 $0

0 $0

111 $774

0 $0

15 $44,016

3802 $323,136

0 $0

0 $0

0 $0

0 $0

0 $0

0 $0

0 $0

0 $0

281 $1,964

40 $200

358 $1,072,848

106685 $9,068,208

14 $162

0 $0

0 $0

72 $432

0 $0

0 $0

0 $0

0 $0

SECTION 1 $6,626,976

TOTAL QUANTITY TOTAL COST

16684 $216,892

0 $0

680 $108,800

SECTION 2 $2,079,267

TOTAL QUANTITY TOTAL COST

3379 $43,930

42 $2,328

0 $0

SECTION 3 $9,238,248

TOTAL QUANTITY TOTAL COST

3168 $41,184

0 $0

0 $0

SECTION 4 $14,352,728

TOTAL QUANTITY TOTAL COST

88904 $1,155,752

169 $9,313

140 $22,400

$329,149

$2,031,764

0 $0

$46,627

9 $30,654

$421,883

0 $0

$41,958

8 $29,176

$255

$396,328

0 $0

$1,189,628

180 $629,328

0 $0

$0

$594

$13,620,359

0 $0

$0

$0

$10,770,384

$1,607,363

$252,423

$1,527

0 $0

$0

$2,376

$252,423

GRAND TOTAL

112,135

212

820

0

922

62

457

232

134,562

32

38

3

252

14,784

2,053

2,738

684

8,213

GRAND TOTAL COST

$1,457,758

$11,641

$131,200

$0

$6,453

$311

$1,369,622

$812,946

$11,437,790

$378

$450

$36

$1,512

$192,192

$14,373

$13,689

$23,956

$8,213

ENGINEER'S COST (12%)

$32,297,219 $25,000 $3,875,666

PROJECT TOTAL ESTIMATED COST

$36,197,885

GRAND TOTAL CONSTRUCTION COST RIGHT OF WAY COSTS

NOTES: 1) TYPE 6 CURB SHALL BE INSTALLED ON BOTH SIDES OF THE ROADWAY. ENTRANCES/DRIVES WILL BE SAWCUT WHERE NEEDED.

9) NO LEFT TURN SIGN SHALL INCLUDE 30 INCH R3-2, ACCORDING TO ODOT, AND PLACED AT A 6 FOOT HEIGHT ABOVE THE GROUND

2) FOR THE RIGHT-IN RIGHT OUT A 6" CONCRETE TRAFFIC ISLAND WILL USED AND INCLUDES 42.33 SQUARE YARDS OF ITEM 609, 6" CONCRETE TRAFFIC ISLAND.

10) STOP SIGN SHALL INCLUDE FABRICATION OF 30' X 30" STOP SIGN AND INSTALLATION

3) SERVICE ROAD: INCLUDES THE FOLLOWING PAVEMENT BUILD-UP FOR A 12' LANE; 3" OF ITEM 448 ASPHALT CONCRETE, 4" OF ITEM 301 ASPHALT CONCRETE BASE AND 6" OF ITEM 304 AGGREGATE BASE. TWO-WAY ROADWAY IS FOR 24 FEET OF PAVEMENT AND ONE-WAY IS FOR 12 FEET OF PAVEMENT.

11) ONE WAY SIGN SHALL INCLUDE FABRICATION OF A 36" X 12" ONE WAY SIGN AND INSTALLATION

4) EXCAVATION SHALL INCLUDE THE REMOVAL OF ALL PAVEMENT INCLUDING BUT NOT LIMITED TO DRIVEWAYS, ASPHALT CONCRETE AND NATURAL SOILS.

12) GROUND MOUNTED SUPPORT: INCLUDES 12 FOOT YIELDING POST AS NEEDED

5) EMBANKMENT SHALL INCLUDE THE REPLACING OF SUITABLE MATERIAL IN THE MEDIAN AND BEHIND THE CURB LINE.

13) TYPE 6 CURB (MEDIAN): INCLUDES TYPE 6 CURB INSTALLED IN THE CENTER OF THE ROADWAY FOR THE PURPOSED OF CREATING A LANDSCAPED MEDIAN

6) CATCH BASIN SHALL INCLUDE CATCH BASIN NO. 3 ALONG THE CURB LINE EVERY 250 FEET ON BOTH SIDES OF THE ROADWAY.

14) TOPSOIL FURNISHED AND PLACED: INCLUDES FURNISHING AND PLACING 3" OF TOPSOIL IN THE LANDSCAPED MEDIAN AREA.

7) MANHOLE SHALL INCLUDE MANHOLE NO. 3 PLACED DOWN THE CENTER OF ROADWAY EVERY 500 FEET.

15) SEEDING AND MULCHING: INCLUDES PREPARING AND INSTALLING SEEDING AND OR MULCHING IN THE LANDSCAPED MEDIAN AREA

January 2007

Page 4-13