Subject: [Fwd: Sparton - Monthly Report for Month of July 2000] Date: Mon, 07 Aug 2000 12:36:46-0600 From: James Bearzi Reply-To: james_bearzi@nmenv .state.nm. us To: [email protected] Carl, not sure if you got this. BRZ

Subject: Date: From: To:

Sparton - Monthly Report for Month of July 2000 Mon, 7 Aug 2000 10:52:14 -0600 "Tony Hurst" "Michael Hebert" , "James Bearzi" CC: "Baird Swanson" , "Mark Schmidt" , "Dennis McQuillan"

Attached is the monthly report for the month of July 2000. Let me know if you have any questions.

Tony PS: Please note that I have switched back to my original Phone number (505-864-1831). Unfortunately however the calls are currently automatically routed to my Cell phone (505 459 4630- courtesy USWest, now called Qwest) since they anticipate some months befor a REAL line connection can be made. Sorry if this is inconvenient to anyone.

~080300REP.doc

1 of I

Name: 080300REP.doc Type: Winword File (application/msword) Encoding: base64

08/08/2000 10:52 AM

HURST ENGINEERING SERVICES P.O.

Box 220 *Bosque, N. M. 87006 *(505) 864-1831 or 459-4630 Email: [email protected]

MONTHLY PROGRESS REPORT For month ending July 31 2000 CV-97-0206 (D.N.M) Albuquerque v. Sparton Technology, Inc. 08/03/00

Tasks Completed: Groundwater Monitoring Plan Reviewed the draft semi-annual annual progress report. Relieved pressure on all monitoring wells. Public Involvement Plan The Public meeting was held July 6th at 7:00pm at 1510 Ellison Drive NW. Attendees included Representatives from the NMED (and HMB), City of Albuquerque (Public Works, Health Dept.), Melloy Dodge, and 5 members of the Public. The meeting started at 7:00pm and was finished by 8:15pm. All questions raised were addressed completely and to everyone's satisfaction. Action items included proposing to EPA that a small map be included with next years information letter showing the most recent available plume boundary. Offsite-Containment System The system ran 100% of the time, and pumped 10,150,400 gallons (average of220 gpm). Continued to work on the proposed contract with US Filter (Chromium treatment). Assessment of Aquifer Restoration

Soil Vapor Extraction System. Melloy Dodge continues remodeling buildings at 9621 Coors Boulevard NW. Additional noise abatement measure on July 5th included adding two mufflers to the exhaust stacks. The noise level was further reduced. The 400 CFM blower system ran 90% of the time this month. Remodeling activities resulted in 72 hours of system down time (July 21 st_24th). Source Containment System Pursued permitting issues: These included o The application for water rights with the State Engineers Office was obtained July 13th. o The USBR misplaced the application for the water rights lease with the Village of Los Lunas (Applied 2/7/00). Reapplied mid July. o It is believed that all issues have been resolved for the following, and the license agreements are expected in mid August.

1

HURST ENGINEERING SERVICES P.O. Box 220 • Bosque, N. M. 87006 • (505) 864-1831 or 459-4630 Email: [email protected]

• •

The license agreement for an easement crossing with the City of Albuquerque for the well pipeline (Applied 4/6/00). A license agreement for an easement crossing with AMAFCA for the well pipeline (Applied 4/6/00).

Changes were made to the Financial Assurance submission per comments received and the plan was issued mid July.

Tasks Planned: Groundwater Monitoring Plan Quarterly monitoring of the wells. Meet with the Contractor and Engineer on the SAD protection issues.

(15th

August) to review wellhead

Public Involvement Plan Offsite-Containment System Assessment of Aquifer Restoration Soil Vapor Extraction System. Source Containment System Continue to pursue license agreements. The Construction work plan being prepared for regulatory review will be issued following receipt of all licenses and agreements.

Continue to update Taylor Ranch reference materials.

Problems Encountered or Anticipated: Permitting (easement) issues remain a potential issue.

By:

Tony Hurst Project Coordinator for Sparton.

2